5 of 5 · Start now · for Jibrael, if he's up for it
One cost sheet for every house
Who keeps it
It works best with one keeper. Jibrael's accounts background makes him a natural fit, and the sheet is laid out so he doesn't need site experience to keep it. That's his call and yours, so ask him first.
The tabs
- How it worksThe rules below, inside the workbook.
- HousesOne row per house. Its totals fill themselves in.
- CostsEach cost line for each house: the budget, then the one price you agreed.
- PaymentsEvery payment that goes out, once.
Three rules
One agreed price per line. Put in the price you said yes to. Leave competing quotes out, or they get added together.
Changes go in their own column. If the price moves, put the agreed change in "Changes agreed" and keep the original price.
Log each payment once. An invoice and its receipt are the same payment.
What it looks like
The Costs tab for a made-up house. Part-payments don't hide what's still owed: the plasterer has been paid £2,000 of £5,400, so £3,400 still shows.
Swipe the table sideways to see every column.
| Cost line | Budget | Agreed | Changes | Forecast | Paid | Still to pay | Over / under |
|---|---|---|---|---|---|---|---|
| Strip-out | £1,500 | £1,400 | – | £1,400 | £1,400 | – | -£100 |
| Damp | £2,000 | £2,300 | – | £2,300 | £1,000 | £1,300 | £300 |
| Plaster | £5,000 | £5,000 | £400 | £5,400 | £2,000 | £3,400 | £400 |
| Electrics | £4,000 | not yet | – | £4,000 | – | £4,000 | – |
| Example house | £12,500 | £13,100 | £4,400 | £8,700 | £600 |
Example Figures are made up. ▲ means heading over budget. Until a price is agreed, the forecast uses the budget.
How it helps us
This is the same information we asked for: budget, agreed price and paid, per house. If Jibrael fills it in for two or three houses, that answers our data ask too.